MANAGEMENT

Safescape replaces ladderway at Nifty

Steel ladderways are being replaced with systems built specifically for the harsh mining environment

Staff reporter

This article is 7 years old. Images might not display.

PRESS RELEASE: While all mines experience corrosion to some degree, most of Australia’s base metal mines face this issue on a daily basis. Safescape Laddertube escapeways are made from polyethylene and stainless steel so they are not subject to the same corrosion issues that steel ladders are.

A recent routine inspection at the Nifty copper mine in Western Australia found that a 160m section of its oldest steel ladders, which extend from the old open-pit mine down into the underground workings, had been deemed unsatisfactory due to excessive corrosion.

At this point Metals X began to search for suppliers to replace the existing compromised steel ladderway. Most options were either unsuitable for the length (over 150m of ladders) or would take up to six weeks to fabricate and deliver. The mine had to be closed until the ladders could be replaced, as escapeways are typically installed on the critical path to production, so a short turnaround to replace this ladder was critical.

Archived article: image not displayed.

Fortunately, an order for another one of Safescape’s customers in the US was awaiting shipment and therefore the ladders were available to be delivered within days. The production team at Safescape’s facility in Perth worked through the weekend to replace the order for their US customer so that it wouldn’t miss its sailing date. Installers were re-tasked and equipment was sent immediately to Nifty.

The next process for the Safescape Laddertube technicians and the mine site was to install the ladderways safely and efficiently. The Safescape team provided the required certified winching and ancillary equipment to lower the ladders underground. However, a further challenge for this particular project was that no vehicular access exists to get to the ladderway into the pit for the first step in replacing the failed section underground.

Nifty personnel searched the country and found a helicopter that was both capable and available to lift the ladders and installation equipment into the pit. While this work was going on, Nifty personnel undertook the inherently dangerous task of removing the compromised ladderway. They did this by undertaking a risk assessment and re-securing the old steel ladderway from top to bottom and then removing in sections from the bottom up, thereby mitigating the risk of a major failure occurring during the removal process.

During this downtime at Nifty, all personnel involved in re-instating the ladderway worked as a well-oiled machine. Meanwhile, the rest of the team worked to get ahead of maintenance, planning and training so that none of the time taken away from production was wasted.

Archived article: image not displayed.

Allan King, chief operating officer at Metals X, commented: “This was a truly exceptional outcome and provided a classic example of the support needed from time to time in this industry. We were fortunate that the ladders were available and are relieved that Safescape were, with the assistance of their dedicated workforce, still able to meet their original order for the ladders sent to the US. It was not only the ladders that they provided but a full installation system to Australian Standards, meeting all the regulators requirements and saving further time.

“A big thanks also goes out to United Aero Helicopters who were able to supply the helicopter required to lower all equipment and infrastructure into the pit and to all those involved and providing support in the installation process. Nine days from order to installation complete under normal circumstances is a great effort but under the circumstances for this job, it can only be described as fantastic.”

All of the ladderways were installed by Friday August 25 and approval from the Department of Mines and Petroleum (DMP) to resume work on the site was received by lunchtime that same afternoon.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets