MANAGEMENT

Mogalakwena upgrades pumps in secondary mill circuit

Mogalakwena increased throughput and reduced energy consumption with a Warman MCR 450 pump

Staff reporter
A Warman MCR 450 installed at the Mogalakwena mine

A Warman MCR 450 installed at the Mogalakwena mine

The pump solution, equipped with a rubber lining and metal impeller, was provided by Weir Minerals Africa.

The mine, near Mokopane in South Africa's Limpopo province, is the world's largest open-pit platinum mine with one of the lowest operating costs. In line with the mine's focus on productivity, Weir Minerals Africa proposed this pump solution as it offered a higher volumetric capacity in anticipation of future increases in throughput requirements.

The large impeller of the Warman MCR pump allows lower pump speeds and consequently less wear than many other pumps, while the rubber liner of the Warman MCR pump is lighter and the hydraulic design has improved efficiency and wear characteristics. This allowed the mine to raise its production target from 600,000 to 700,000 dry tonnes per month.

The replacement pumps were retrofitted to the existing footprint, without disturbing existing motors, gearbox drives or pipework. On-site Weir Minerals Africa technicians were deployed during the commissioning phase. Once installed, the Warman MCR 450 pump milled 4,400m3/h, shifting 760,000 dry tonnes per month.

Online for 78.9% of the plant operational time, the pump was able to deliver significant savings through lower power consumption. After 3,000 hours in operation, the Warman MCR 450 pump was examined to evaluate the wear rate of the hydraulic components. Localised wear was evident on some of the components, and the mine decided to continue running the pump to point of failure. Weir Minerals Africa stated that the improved wear life will result in a significant saving for the customer.

The independent study conducted after the initial installation confirmed the pump's improved performance. The study also recommended converting all mill discharge pumps at the operation to Warman MCR 450 pumps, to maximise pump performance and reduce energy consumption.

Based on the mine's satisfaction with the way the pump met its objectives, it has placed an order for three Warman MCR 450 pump conversion kits to retrofit the remaining Warman AH 20/18 RE pumps installed in the secondary mill circuit.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production