PROCESSING

Stage Two of Kilimapesa plant completed

PRESS RELEASE: Installation of Stage Two of the new processing plant at the Goldplat’s Kilimapesa gold mine in Kenya was completed in mid-June 2017

Staff reporter
Stage Two involved the installation of the crusher circuit and three additional leach tanks

Stage Two involved the installation of the crusher circuit and three additional leach tanks

This comprised a new crusher circuit and three additional leach tanks. Although installation was slightly delayed due to difficulties getting certain steelwork and electrical supplies to the site, commissioning has begun and is expected to be completed by the end of June. Furthermore, despite the delays, planned mill throughput rate for Stage Two of 120t/d of ore was achieved during May. This was made possible by treating previously stockpiled fine material which did not require crushing, as well as by the relocation and installation of a spare crusher as a temporary measure.

A strategic decision has been taken to bring forward the switch over to grid power in order to overcome ongoing difficulties with the generators, primarily a result of poor diesel quality. In order to facilitate the financing thereof, an agreement has been reached with the Kenya Power and Lighting to allow payment of the installation cost of approximately US$200,000 to be spread over 12 months. Installation is expected to begin towards the end of June and is expected to take 6-8 weeks.

Major improvements to the supply of grid power have also been completed by Kenya Power making this source far more reliable, both for the old as well as the new plants. This should have a positive impact on costs as fewer switch-overs to diesel back-up power will be required. Once consistent planned production and profitability have been achieved with Stage Two, a decision will be taken regarding the Stage Three expansion. The b oard has however approved the installation of the second mill (originally planned for Stage Three), specifically as a standby to mitigate downtime risk.

Gerard Kisbey-Green, CEO of Goldplat, commented: “Kilimapesa is now operating profitably and at the increased rates targeted for Stage Two. The overall performance of the group remains positive and in line with market expectations.”

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions