SURFACE

Mining kicks off at Aurizona

Equinox Gold is progressing toward production and first pour later this year at Aurizona

Staff reporter
 Equinox Gold's Aurizona gold operation in Brazil

Equinox Gold's Aurizona gold operation in Brazil

Contractor U&M Mineração e Construção was mobilised to the site in March, and mining commenced in mid-April, officials said late last week. Most staffing has been completed, and a majority of the mine's fleet is on-site.

With construction work now under way, the miner's goals include removal of waste from two areas of the Piaba pit and access road development. To help do that U&M is operating two shifts a day and at the start of June will implement a third shift to mine 24 hours a day, seven days a week.

Ore mining should begin, Equinox said, during the September quarter, and once online it will be the company's first operating mine. Average production is projected to be 136,000oz/y.

"While the Aurizona operations team is focused on achieving production, Equinox Gold's exploration team is focused on mine life extension and district-scale opportunities," said CEO Christian Milau, noting that a resource update is in process to tie in findings from its 2017 exploration programme.

As of the end of March, the miner said the overall project was 44% complete and EPCM activities were at the 61% mark. Plant construction was 27% complete at that same time.

Carbon-in-pulp (CIP) circuit and detox tank refurbishments are now done, as are the concrete foundations and pedestals for the new sag and ball mills. Semi-autogenous grinding (SAG) and ball mill manufacturing has wrapped up and the components are en route with expected delivery in June.

To date, Equinox has spent US$43 million of the project's US$146 million construction budget, and another US$76 million is committed.

The company had completed 44% of the overall project and 61% of the engineering, procurement and construction management (EPCM) activities at the end of March.

A total of US$43 million from the project's US$146 million construction budget has been spent to date, while an additional funding package of US$76 million was pledged at the end of March.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production