Fort Knox opens door to expansion

With a go-ahead for the Gilmore expansion, Kinross is eyeing six additional years of mining

Staff reporter

This article is 6 years old. Images might not display.

Officials said the initial project will extend mining by six years to 2027, and leaching will go through 2030.

With the US$100 million expansion, production over the life of the mine will also grow by about 1.5 million equivalent ounces. Also by the end of its life, Kinross estimated, the complex will have processed an additional 183 million tonnes.

The Gilmore project plan has been optimised to keep initial capital costs lower, so it will involve minimal construction of new infrastructure or new equipment purchases. This includes, Kinross noted, continuing mining using Fort Knox's current fleet and leveraging assets from its other operations in North American when replacement equipment is needed.

Initial work on the new heap leach and dewatering is expected to begin in the September quarter, with a stripping start projected next year. It should see initial production from Gilmore in early 2020.

About 5% of Gilmore's ore will be stacked on the existing pad, and 95% of it will be stacked on the new heap-leach pad. Stacking will also begin in 2020, with milling to follow late that year.

Kinross officials said contracting is now under way and a project team to oversee progress has been formed. The permitting phase is moving along as planned, it added, and engineering is largely complete, and permits are present to start work on the mine's new heap-leach pad.

President and CEO J Paul Rollinson said the company is happy to be moving forward with the brownfield expansion and called Fort Knox one of its top performing assets.

"The Gilmore project offers an attractive IRR and NPV and adds to our suite of quality development projects at Tasiast, Round Mountain, Bald Mountain and Kupol to enhance our globally diverse portfolio," he said, adding that the initial capital cost will be funded by the mine's cash flow, which will aid it in keeping a strong balance sheet and maintain its financial flexibility.

"With additional upside potential at Gilmore and beyond, Fort Knox is a significant asset in our portfolio located in an excellent mining jurisdiction. The Gilmore project and the addition of estimated mineral resources improves value and is expected to be a key contributor to the future growth of our company."

Kinross owns 100% of the open-pit Fort Knox mine, which is located northeast of Fairbanks.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets