SURFACE

Lindero keeps edging closer to start-up

Fortuna Silver Mines' Lindero project in Argentina is still aiming for an operations start in 2019

Staff Reporter

This article is 6 years old. Images might not display.

Vancouver, Canada-based Fortuna, which wholly owns Lindero in the Salta province, said that the delays stemmed from the building and expansion of the site's camp facilities and had a limiting factor on certain contracts. However, the timeline compression has moved the start from early in the September quarter of next year to late in the same quarter.

President and CEO Jorge Ganoza added that there has been a progressive pick-up on field activities at Lindero, and it has a worker count now of 330 as it moves toward peak employment of 950.

The mine took delivery of three pieces of Komatsu mine equipment in mid-July, including two graders and a dozer. Eleven more machines, including six 100t trucks and two 17y3 wheel loaders, are on schedule for September deliveries, and the final delivery of two mine production drill rigs will be made in November.

Fortuna is targeting a December start to mine development activities, with drilling and blasting to follow in March of next year.

"With a large portion of our major contracts awarded, our project team is working on opportunities to further optimise the sequencing of concrete, electromechanical and piping installations to streamline the project's schedule," Ganoza noted.

"Mass earth movement and leach pad construction, one of the initial and largest field activities, is at full gear now after a slow start and is advancing according to plan for completion in the [June] quarter of 2019."

Lindero's engineering work is currently between 70% and 100% complete for all slated projects, permitting construction start on all its scheduled fronts.

As of the end of June, Fortuna said its total cash spent on Lindero's construction for this year along has been US$38 million. Of that, $31 million was spent in the June quarter.

It is projecting a total 2018 spend of $150 to $175 million.

The planned open-pit Lindero, which has an anticipated 13-year mine life, first commenced construction in September 2017.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets