UNDERGROUND

Mt Morgans on target to go for gold

Mt Morgans commercial production to begin this month

 Dacian is aiming for a production target of 180,000 to 210,000 ounces whole-year

Dacian is aiming for a production target of 180,000 to 210,000 ounces whole-year

Company officials said ore development has commenced at the Allanson underground production decline, its third at the Westralia mine area. Mining is still ongoing at the first two declines, Beresford South and Beresford North, with stope work set to begin at the latter in the coming days.

"As mining activities continue across all three production declines at Westralia (Beresford South, Beresford North and Allanson), and open-pit mining at Jupiter is advancing well, achieving MMGO's commercial production milestone by end of this month remains on track," it said of the 100% company-owned operation near Laverton.

Dacian is now targeting a commercial production milestone from Westralia of approximately 3,000t per day of high‐grade ore to the Mt Morgans treatment plant; the miner's production plan outlines 1,000t/d from each underground production decline at Westralia tied to combined stoping and development activities.

It is on its way to that goal, the miner added, as at the end of the September quarter Westralia was operating at about 1,900t/d - the majority of its ore coming from the Beresford South stoping and ore development. The company noted that the trio of operational production areas at Westralia are spread over a distance of 1.8km.

Executive chairman Rohan Williams said it is still on target to meet its guidance range of 180,000‐210,000oz whole-year with production increasing progressively in each quarter.

"The project is ramping up in line with our schedule across both the underground and open-pit mining operations," Williams said.

"The start of ore development at our third underground production decline at Allanson marks another important step in the ramp‐up with mining activities across all three underground mining centres. This, together with continued strong progress at the Jupiter open pit, means we are confident of achieving commercial production, as planned, by the end of 2018."

In addition to Westralia, the project also includes the Jupiter operation, which commenced open-pit mining earlier this year.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production