UNDERGROUND

Ivanhoe's Kakula ahead of schedule

Eight kilometres of underground development now completed at DRC project

Staff reporter
Aerial view of Kakula’s main declines, ore stockpiles, workshops under construction and the first phase of accommodations

Aerial view of Kakula’s main declines, ore stockpiles, workshops under construction and the first phase of accommodations

The mining company's co-chairs Robert Friedland and Yufeng ‘Miles' Sun announced that more than eight kilometres of underground development has now been completed; this puts the project 1.7km ahead of plan.

The development crews are operating semi-autonomous mining equipment, including double-boom jumbo drills and 50-tonne trucks.

The mine team is currently also transporting development ore to surface and storing it at pre-production stockpiles, which are expected to grow to around 1.5 million tonnes of high-grade ore and an additional 700,000t of material grading around 1% to 3% copper prior to the start of initial production in 2021.

Based on the results of the February 2019 Kakula pre-feasibility study, Ivanhoe projects Kakula's average feed grade over the first five years of operations to be 6.8% copper, and 5.5% copper on average over a 25-year mine life.

Kakula's original 3-million-tonne-per-year first processing plant module was redesigned during the basic engineering phase to a nameplate capacity of 3.8Mt/y. The company has placed purchase orders for all major long-lead time mechanical equipment, while plant earthworks are complete and civil works are advancing.

Two low-entrainment flotation Jameson cells have already been delivered to site; these will be used as cleaner cells to produce the final cooper concentrate before thickening and filtration.

By April of this year, a conveyor system will start transporting broken ore from underground to the surface processing plant.

The current updated estimate of the project's initial capital costs is around US$1.3 billion.

Ivanhoe said other engineering and construction activities underway at Kamoa-Kakula include the refurbishment of six turbines at the Mwadingusha hydro-electric power plant and associated 220-kilovolt infrastructure, finishing construction of a permanent road between the mine site and the Kolwezi airport, construction of the first phase of accommodations for 1,000 employees and contractors, and other surface infrastructure.

Work on the power plant, projected to deliver approximately 72 megawatts to the national power grid, is being conducted by engineering firm Stucky of Lausanne under the direction of Ivanhoe Mines and Zijin Mining, in conjunction with the DRC's state-owned power company, La Société Nationale d'Electricité (SNEL).

Out of the 4,400 employees and contractors currently constructing the Kakula mine around 90% are Congolese nationals.

The company is also progressing with an independent Kakula definitive feasibility study and an updated integrated development plan for the whole Kamoa-Kakula mining complex; this is expected to be issued later this year.

The project is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global (0.8%) and the DRC government (20%).

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production