This article is 4 years old. Images might not display.
The 3.65-million-tonnes-per-year mine in northwestern Botswana has made a series of inroads for its planned trio of underground mines. Construction, completed by Kalcon and managed by Fluor, has involved the development of three boxcuts, each situated in 40 metres or more of sand cover, with 1.3 million cubic metres of material excavated for each.
As ready, each boxcut was handed over to Perenti's Barminco Mining Services Botswana, which began its work in February.
As of April, the mining operator confirmed it has achieved 1,000m of underground development at the Central, North and South mines, together forming the Zone 5 mine.
Additionally, the construction of earthworks and infrastructure at the Zone 5 mining surface, which was contracted to Concor Botswana and Kalcon, respectively, has been ongoing and progressively turned over to Barminco. Their work includes internal roads, terraces, run-of-mine pads, interim workshops, fueling facilities, a 650-person camp and offices.
Khoemacau Copper Mining Pty said that the demolition works for the processing plant, contracted to SMEI, and civil works, contracted to Concor Botswana, for a new HIG mill are ready for construction for steel erection and equipment installation.
Finally, the final layer of an access road and a mine haul road are set for completion by the end of the year, and Conco's 132kV of power supply infrastructure to the site is also being worked on. That project includes a 50km transmission line from the Botswana Power Corporation Legotlhwane substation; solar power use is also being evaluated.
Zone 5 has a mine life exceeding 20 years. Its processing plant is being upgraded to process 155,000t to 165,000t of copper concentrate annually that contains about 60,000t to 65,000t of payable copper and 1.9 million oz of silver.