MANAGEMENT

Commissioning underway at Brucejack

Wet commissioning is nearing completion at the Brucejack underground gold mine

Staff reporter

This article is 7 years old. Images might not display.

The commissioning process was initiated in April and the first ore has been introduced to the process in preparation for production.

Construction of underground infrastructure, including the crusher, rock breaker, feeder, electrical substation, conveying system and transfer towers is substantially complete and commissioned. The conveyor gallery from the Valley of the Kings portal to the mill building has been installed and the conveyor has been commissioned. 900t of ore has been introduced as part of the commissioning process and run through the crusher and conveyed to the surge bin in the mill building.

Commissioning of the process plant and service systems is progressing. The variable frequency drives for the SAG and ball mills have been tested and commissioned, with electric motors bumped and drives coupled. Water has been introduced into both mills and water load test operation has been completed. The rougher floatation cells have been hydro tested and blowers and compressors have been commissioned. The semi-autogenous grinding (SAG) mill feeders and conveyors have been commissioned, as has the recirculation high angle conveyor. Services such as process and fresh water, instrument air, pump gland water have been commissioned and are in service. The fire pumps have been commissioned. The company remains on track for the production of gold concentrate and doré in the coming weeks.

Power from the 57km-long transmission line connecting the Brucejack mine to the BC Hydro power grid is now fully integrated and powering the entire mine site with high voltage commissioning completed. The switch gear and electrical distribution within the mill building and the Valley of the Kings portal building has been commissioned and is being energised as subsystem installation is completed. The process control communication system infrastructure installation is substantially complete with the DCS operational control system implementation and testing ongoing.

Underground development continues to advance and the hand-over from the construction team to the operations crew has been completed. Over 187,000t of ore has been stockpiled on surface and underground. Two long-hole drills are currently drilling off stopes. The slot raise and slot in the test stope have been blasted. The test stope is ready for production and four other production stopes are being drilled.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets