SURFACE

Gold Road still eyeing mid-2019 for Gruyere start

Gold Road Resources is still on track for a 2019 June quarter start for the Gruyere gold project

Staff Reporter
The Gruyere project in Western Australia is on track for a June quarter 2019 start

The Gruyere project in Western Australia is on track for a June quarter 2019 start

As of July 27, the Perth-based miner said overall project engineering is now 94% complete, while construction is now at the 61% mark. EPC construction of the process plant and associated infrastructures is 39% done.

Two projects at the complex outside of Laverton, the Yamarna gas pipeline and the Gruyere power station, have been wrapped up ahead of schedule. Commissioning is expected during the September quarter.

Gold Road officials also confirmed that all of the project's long-lead items - including the SAG and ball mills - have been delivered to the site from Perth. They are now awaiting installation by its EPC contractor Amec Foster Wheeler Civmec Joint Venture (ACJV).

"Activities by the ACJV on the Yeo borefield continue, with a significant portion of the pipes welded and pressure testing in progress," the company said. "The installation of the overhead powerlines is well advanced, with the majority of poles installed and conductor installation approximately 50% complete."

While a small section of the north Yeo Borefield was impacted by flooding, resulting in no activities having commenced there at this time, Gold Road said it does not anticipate the obstacle will impact plant completion and start-up.

Flow rate testing returned figures slightly above the estimates of the project's feasibility study, it said. Commissioning planning is well advanced, and early commissioning activities will begin during the final quarter of the year.

MACA completed the main bulk earthworks in June. A second package of work is now in process, and it is now busy on a second package of work.

The retained mining services contractor, Downer EDI, is progressing well with mining and workshop facilities construction. That should be completed during the September quarter.

Downer's workforce is targeting mobilisation in the December quarter for the beginning of pre‐strip activities on the Gruyere open-pit by early 2019.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production