MANAGEMENT

Order delays drive up costs for Ascot

The process plant cost also increased by C$8 million due to supply chain pressures and inflation.

Capex for the Premier gold mine increased 27% due to supply chain issues and inflation.

Capex for the Premier gold mine increased 27% due to supply chain issues and inflation.

Supply chain delays have driven up costs for Ascot Resources' Premier Gold mine in northwestern British Columbia.

The new capital cost for the mine is estimated to be C$224 million, 27% higher than the March 2021 capital cost estimate.

Indirect and owners costs have increased by C$30 million, due to the increased length of workers needing to stay on-site due to delivery delays and COVID-19.

The cost of the process plant also increased by C$8 million due to supply chain pressures and inflation, Ascot said.

Ascot also had lost several pieces of equipment at sea, and has submitted orders for the re-fabrication of the replacement water treatment plant clarifier and tailings thickener. These should be delivered by April.

Ascot has built in a month-long contingency on this delivery date.

Weather impacts, piping and instrumentation labour productivity, and indirect cost inflation are also to blame for the price increases.

Ascot is still on track to achieve first gold pour in the January quarter of 2023. Mill commissioning is targeted for later in 2022.

Mine construction is 23% complete, and Ascot will focus on underground development of underground operations, as well as the delivery and installation of the new water treatment plant in 2022.

The water treatment plant is expected to be completed by November.

Also slated for this year is the completion of the Cascade Creek diversion channel, the tailings facility earthworks, and the completion of the process plant circuit.

Supply chain pressures and inflation have led to increased construction costs across the sector, Marsh Mining Practice Leader Raul Munoz said.

"What we've seen is that over this year, there have been significant delays not just on construction of new mines, but also with mines that are producing," he said. "There have been significant issues with the shipment of reagents which are useful in processing."

The majority of delays have not affected long-lead items, he said.

Delays in shipments will continue to be affecting mining deliveries for some time.

"It's going to have an impact for the rest of this year, for sure," he said.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets